Week 3

Sarah and I really buckled down and wrapped up the drawings for the Green Heart Garden project. It took longer than I expected it to take because of conforming to the firm’s graphical standards. It was also a new challenge to work on a project concurrently with someone. We had split up elevations and plans […]

Intro Week + Green Heart Garden

[Sorry I originally posted this in the wrong place…] I started working at Synchronicity last week. The first week was mostly onboarding activities to get used their process. I tagged along for a construction site visit to check on the progress at Old Village Post Inn in Mount Pleasant. Its a renovation of the existing […]

Weeks 1 & 2 Jan 13-23

Week 1 Mon Jan 13 4 hours: Practice Management, P&D, P&A monday office meeting restaurant 1 elevations formatting engineering client site visit, schematic plans Tues Jan 14 4 hours: P&A,  Project Management, engineering client design meeting, schematic plans, as-builts Wed Jan 15 4 hours: Project P&D, P D&D, C&E Summerville Retail: elevation signage changes cad, […]

Week 1-2: January 13-16 and January 20-23

Week 1:   1.13.20 Hours Worked: 8 am-12 pm Total Hours: 4 Tasks Completed: First day orientation – setting up computer, email, familiarizing myself with documents and computer organization Began looking at past Historical Assessments to understand the firm’s approach and graphic style AXP Credit: Practice Management   1.14.20 Hours Worked: 8 am-12 pm Total […]

Week 1: 1.14 + 1.16

1.14.20 Hours Worked:8am-5pm Total Hours: 8  Tasks Completed: First day orientation – setting up computer, email, downloading basic programs Rendering Updates in Photoshop: Adding Donor Recognition to existing renderings in Photoshop. Editing the rendering to best show the recognition via street and building signage. AXP Credit: Practice Management + Project Management   1.16.20 Hours Worked: […]

Week 2: 1/20/20 – 1/23/20

DAILY LOGS Monday, January 20 Hours Worked: 8:00 – 12:00 Total: 4 hours Project Revisions: Carnes Project Revisions: Beaufort AXP Category: Project Development & Documentation Tuesday, January 21 Hours Worked: 8:00 – 12:00 Total: 4 hours Office Meeting Update door schedule Furniture plan – Office AXP Category: Project Development & Documentation and Practice Management Wednesday, […]

Week 1 SOS

Tuesday, January 21 I began working for the non-profit organization, Saving Our Structures. The first day was mostly getting accustomed to the systems they use and reviewing previous surveys of residential buildings that I will be documenting this semester. AXP: C/E 4hrs Wednesday, January 22 I began my journey around town documenting and assessing several […]

Week 1: 1/14/20 – 1/16/20

DAILY LOGS Tuesday, January 14 Hours Worked: 8:00 – 1:00 (1 hour Lunch) Total: 5 hours First day Computer setup (employee checklist) Demolition plan AXP Category: Project Development & Documentation Wednesday, January 15 Hours Worked: 8:00 – 12:00 Total: 4 hours Interior elevation tags Ceiling plan Conference call (sit-in) AXP Category: Project Development & Documentation […]