Overview: I was able to get out of the office this week and make some job site visits as well as a stakeholder meeting at the Old Library. For our job site visits I went with our CA Director out to North Charleston where we have a project under construction for Charleston Library Support Facilities. […]
Month: October 2019
Meadors 10.28-10.29
10.28.19 8:00-12:00 Practice Management Staff meeting, Project Reviews Update Revit template 10.29.19 8:00-12:00 Update Revit template Week Reflection Projects Template Sometimes overlooked, it’s actually very important to have a handle on and set standards for the graphics and visuals in what you produce in a CD set. Just because it’s a technical drawing, doesn’t mean […]
Bulk Blog Entry
Bulk Blog Entry
10/22-10/24
10/22 8:45 – 12:45 Compiling the permit set of Lee Major Residential Addition 3.5 h Construction Documentation 10/23 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/24 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 2.5 h Construction Documentation Weekly […]
10/14 – 10/17
10/14 8:45 – 12:45 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/15 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/16 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/17 […]
10/7 – 10/10
10/07 8:00 – 12:00 Make changes to the lobby design of Lancaster Eye Clinic, study both in plan and section 4 h Project Planning & Design 10/08 8:00 – 12:40 Make changes to the lobby design of Lancaster Eye Clinic, study both in plan and section 4.5 h Project Planning & Design 10/09 […]
Blog Post 10/21-10/24
10/21 – Worked on construction documents for an addition to a Kiawah Residence. 10/22 – Continued working on construction documents for the addition, worked on a wall section for the same project. 10/23 – Continued working on wall section for the addition. 10/24 – Finished working on main wall section and began working on setting […]
A little bit of everything
Monday 21st October 94 Spring (3h – Project Planning and Design) Today we had a Monday weekly meeting where we discuss the projects we are working on and what we have to get done for the week. I then continued to work on facade studies for 94 Spring. I worked on an elevated double balcony […]
TC Blog Post 10/21 – 10/24
Two of the various section drawings that I was tasked with digitizing and adjusting. Lots of red lining and details. Mike Nixon – Project Lead. Savannah Commons Assisted Living Facility Drawing enlarged details and adjustments made throughout the week. Interesting process. Mike Nixon – Project Lead. Savannah Commons Assisted Living Facility Monday 10/21 Out […]
Kelly Umutoni Weekly Entries – Lessons Learned: 10.21.2019 – 10.24.2019
Project title: Spectrum Project Location: Raleigh, NC Project manager: Luke Jarrett Role of the student: Helped set up sheet set Lessons Learned Basic lesson: dimensioning to the finish material on enlarged detail plans like bathroom but dimensioning to the stud or structure line in larger plans.