12/10 9:10 – 12:30 Residential porch addition SketchUp model 3.5 h Project Planning & Design 12/11 9:30 – 12:30 Residential porch addition SketchUp model 3 h Project Planning & Design 12/12 9:30 – 12:30 Residential porch addition SketchUp model 3 h Project Planning & Design Weekly Reflection This is my last week […]
Author: raytan
11/26 – 11/27
11/26 14:00 – 18:00 Opie Market DRB document site context slides 4 h Project Planning & Design 11/27 9:50 – 19:00 Opie Market DRB document site context slides 9 h Project Planning & Design Weekly Reflection Due to the Thanksgiving holiday, I chose to come into the office for a whole day on […]
11/18 – 11/21
11/18 8:50 – 12:40 Opie Market streetscape photoshop 4 h Project Planning & Design 11/19 8:30 – 12:30 Opie Market site photo organizing and context building 3D modeling 2 h Project Planning & Design 11/20 8:30 – 12:30 Opie Market context building 3D modeling 3 h Project Planning & Design 11/21 8:30 […]
11/6 – 11/7
11/06 9:00 – 13:30 Shadow Lane Project pre-design concept sketchup model 4.5 h Project Planning & Design 11/07 9:00 – 13:00 Shadow Lane Project pre-design concept sketchup model 4 h Project Planning & Design Weekly Reflection We got back from HCD and I only worked for two days this week. I don’t really […]
11/12 – 11/14
11/12 8:40 – 12:45 IBC Code Review Built context 3D model for Opie Market Project 2 h Project Planning & Design 11/13 8:30 – 12:30 Built context 3D model for Opie Market Project Site visit, took photos of the surrounding streetscape. 3 h Project Planning & Design 11/14 8:20-12:50 Site visit, took photos […]
10/28 – 10/29
10/28 8:20 – 10:20 Shadow Lane Project pre-design concept sketchup model 2.5 h Project Planning & Design 10/29 9:00 – 13:00 Shadow Lane Project pre-design concept sketchup model 4 h Project Planning & Design Weekly Reflection This is a short week. A+H group is going to NOLA participating Healthcare Design Conference from 10/30 […]
10/22-10/24
10/22 8:45 – 12:45 Compiling the permit set of Lee Major Residential Addition 3.5 h Construction Documentation 10/23 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/24 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 2.5 h Construction Documentation Weekly […]
10/14 – 10/17
10/14 8:45 – 12:45 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/15 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/16 8:30 – 12:30 Compiling the permit set of Lee Major Residential Addition 4 h Construction Documentation 10/17 […]
10/7 – 10/10
10/07 8:00 – 12:00 Make changes to the lobby design of Lancaster Eye Clinic, study both in plan and section 4 h Project Planning & Design 10/08 8:00 – 12:40 Make changes to the lobby design of Lancaster Eye Clinic, study both in plan and section 4.5 h Project Planning & Design 10/09 […]
9/30 – 10/03
9/30 9:30 – 12:20 Discuss with mentor about the Internship Prompt 1 Make changes to the lobby design of Lancaster Eye Clinic 2.5 h Project Planning & Design 10/01 8:00-12:30 Make changes to the lobby design of Lancaster Eye Clinic, study both in plan and section 4.5 h Project Planning & Design 10/02 […]