Autumn Hinson + JMO Woodworks, Week 10.19 – 10.23

Daily Log Tuesday (10/20): Sanded and prepped components for door assembly Glued together medicine cabinet doors for vanity AXP Hours : 4 – Project Development & Documentation   Wednesday (10/21): Drilled pocket screw holes on toe kick for vanity Filled in holes and defects on toe kick legs Milled and sanded components for shelves inside […]

Autumn Hinson + JMO Woodworks, Week 10.12 – 10.16

Daily log Monday (10/12): ¬†Sanded parts for medicine cabinet face frame AXP Hours : Project Development & Documentation – 4 hours   Tuesday (10/13): ¬†Prepped medicine cabinet face frame for wall inset for paint AXP Hours : Project Development & Documentation – 4 hours   Wednesday (10/14): Sanded parts for vanity wall face frame Prepped […]

Autumn Hinson + JMO, Week 10.5 – 10.9

Daily Log Monday (10/5): Sanded frames Sanded jib doors Milled face frames for cabinet fronts AXP Hours : Project Development & Documentation – 4 hours   Tuesday (10/6): Milled and sanded face frame for cabinetry AXP Hours : Project Planning & Design – 4 hours   Wednesday (10/7): Sanded face frames for vanity Glued panels […]

Autumn Hinson + JMO, Week 9.18 – 9.25

Daily Log Monday (9/21): Delivered both end walls to the site AXP Hours: Project Management – 4 hours   Tuesday (9/22): Lifted both end walls onto balcony Installed and shimmed right end wall AXP Hours: Project Management – 4 hours   Wednesday (9/23): Delivered remaining components for installation to site Installed and shimmed left end […]

Autumn Hinson + JMO, Week 9.14 – 9.18

Daily Log Monday (9/14): Moved end wall and outside tower to paint Stood other end wall and tower up for prep Delivered center tower on site Verified and marked locations for other casework AXP Hours: Project Management – 4 hours   Tuesday (9/15): Installed Center Tower on site AXP Hours: Project Management – 4 hours […]

Autumn Hinson + JMO, Week 9/7 – 9/11

Daily Log Monday (9/7): Sanded faces of towers Glued faces of towers Prepped and addressed small details AXP Hours: Project Development & Documentation/Project Management – 4 hours   Tuesday (9/8): Stood up end wall and outside tower Prepped panel openings Sanded glue up residue Glued second end wall and outside tower together AXP Hours: Project […]