Martin Luther King Pool Cover Charleston, South Carolina Project Scope: Our firm is renovating the existing pool in downtown Charleston, the MLK public pool. This renovation includes new landscaping/fencing, an entirely new strucuture covering the pool, a renovation of the existing buildings, and additional parking across the street. Project Manager: Mike Nixon Role of Student: […]
Month: February 2019
Taylor Bissert: Daily Post, Weekly Summary 2/11-2/21
Weekly Overview – Last week at Novus Architects I helped with interior design work for one of our workplace clients. We are currently in a great place; we have TOO much work and not enough support. I gained valuable experience in project management by taking this on by myself. Our interior designer helped guide me […]
Coral Rembert: Daily Blog Post; Weekly Summary 2/18-2/21
2/18 – Worked on Specifications and Electrical RCP’s – The detailing work mainly consisted of detailing electrical RCP’s for a couple different houses using detail lines in Revit. I also went into AutoCad and took existing specs for sheets and converted them over to Revit text files and edited them to look correct on the sheets […]
Ryan Massengill: 2.22.19
Lessons learned: Realized an appreciation for taking the time to produce a jig/ spacers for assembling identical parts. Partially assembled bunk bed platform. Components for bed railings, in the process of being sanded. Sanded components for bed railings, pre-drilled and post dry-fit. Bed railings assembled, glued, and fastened.
Ryan Massengill: 2.21.19
Hours: 8-12 Tasks: Assemble and glue parts for bed railings Produce beveled sapele railing cap
Ryan Massengill: 2.20.19
Hours: 8-12 Tasks: Dry fit parts for bed railings, pre-drill for fasteners
Ryan Massengill: 2.19.19
Hours: 8-12 Tasks: Sand poplar X’s for bed railings
Ryan Massengill: 2.18.19
Hours: 8-12 Tasks: Assemble bunk bed platforms
John Murden: Feb. 18-22 Weekly Logs and Summary
On Monday I continued working on renderings and boards for our Awendaw Fire Station Project. I had been updating the sketchup model based on the most recent modifications so that we would have new rendering for a meeting with the town council and review board. On Tuesday I worked more on the model of […]
Phil Riazzi: Weekly Entry – 02.23.19
Daily Entries 02/18/19 – Monday Time: 8:00am – 12:00pm (4hrs) Tasks: Door schedule, storefront details, door and head jamb details for a new firehouse AXP: Project Development & Documentation 02/19/19 – Tuesday Time: 8:00am – 12:00pm (4hrs) Tasks: Door schedule, storefront details, door and head jamb details for a new firehouse AXP: Project Development & […]