Kayla Pratt – Week Seven

Hours: 9     AXP: 9

This week I was on vacation Monday-Wednesday and worked a full day Thursday. On Thursday I reviewed draft comments from three ARC meetings and also submittal requirements for a renovation/addition in Mount Pleasant. We have been waiting on a survey for a new home in Johns Island to verify our base flood elevation (BFE) which will determine our building height. We received this information this week and because the BFE was higher than we had suspected, our building height was acceptable. I completed the permit set for this new home and sent it to the builder and client for final approval. I also helped with a code analysis for a new veterinary hospital. One of the items we wanted to verify was if we would need a sprinkler system, and based on our analysis we will not – very good news for our client.