Weekly Summary
Time Sheet
11/21/2022 [8:00am-12:15pm]
– Worked with Jennifer to put together some storefront elevation drawings for Home Telecom. I got it about 90% done by the end of my day.
[AXP – 4 HOUR(S) PROJECT DEVELOPMENT & DOCUMENTATION]
11/22/2022 [12:00pm-5:00pm]
– Finished up the Home Telecom drawings and shifted back to 651 King St. work and adjusted the storefronts based on new design. Also started setting up views for all of the plan, foundation, and opening detail sheets.
[AXP – 4 HOURS PROJECT DEVELOPMENT & DOCUMENTATION]
11/23/2022 [7:45am-12:00pm]
– Finished setting up sheets and started doing some general detail work across the drawings for 651 King St.
[AXP – 4 HOURS PROJECT DEVELOPMENT & DOCUMENTATION]
AXP Summary
PROJECT DEVELOPMENT & DOCUMENTATION – 12 HOURS
LESSONS & SKILLS LEARNED
This week I just kind of learned about processes for detailing drawings in Revit and best practices for doing detail work here. Most of my experience has been with AutoCAD so I’m still learning the workflow and best practices for detailing things the way the firm wants them done.
PROJECT IMAGES
651 King St.
Project Manager: Will Morrison
Below: In-Progress detail drawings I worked on.