Weekly Summary
Time Sheet
11/14/2022 [8:00am-12:15pm]
– Had morning meeting where we went over the projects for the week. I’m going to be with Will for the majority of the week working on 651 King St and any P5B3 comments we get from last week.
[AXP – 3 HOUR(S) PROJECT DEVELOPMENT & DOCUMENTATION]
[AXP – 1 HOUR(S) PROJECT MANAGEMENT]
11/15/2022 [12:00pm-5:00pm]
– Adjusted some materials in the renderings for P5B3 for Will. Then went back to work on some of the storefront items for 651 King St.
[AXP – 4 HOURS PROJECT DEVELOPMENT & DOCUMENTATION]
11/16/2022 [8:00am-12:00pm]
– Started work on the RCP for 651 King St.. Worked on all of the floors’ RCP plans and worked with Will to get a better idea of the project.
[AXP – 4 HOURS PROJECT DEVELOPMENT & DOCUMENTATION]
11/17/2022 [8:00am-12:00pm]
– Worked more on the RCP for 651 King and got it completed by the end of my day for all 3 floors of the building. Put comments on the drawing and sent to Will.
[AXP – 4 HOURS PROJECT DEVELOPMENT & DOCUMENTATION]
AXP Summary
PROJECT DEVELOPMENT & DOCUMENTATION – 15 HOURS
PROJECT MANAGEMENT – 3 HOURS
LESSONS & SKILLS LEARNED
This week I just kind of spent time working on learning the office’s standards for RCPs. I’ve done them a million times before but making sure notes are in the same place as expected was a a big goal of mine today.
PROJECT IMAGES
651 King St.
Project Manager: Will Morrison
Below: In-Progress RCP plans from the week.