Jed Donkle | GBA | Week 4

October 10, 2022 [4 Hours]

  • Monday Meeting
    • AXP Hours: 1 (Practice Management)
  • North Charleston Senior Center, Carner Ave.
    • Continued working on redlines from previous week.
    • Accepted design option to eliminate windows from above and below the canopy.
      • AXP Hours: 1.5 (Project Development & Documentation)
    • Charleston County Community Development & Housing Renovation
      • Added elements to the reflected ceiling plan based on the drawings sent to us by the MEP consultant.
      • Made a PDF of the drawing set to send to the price estimator.
        • AXP Hours 1.5 (Project Planning & Design)

October 11, 2022 [4 Hours]

  • North Charleston Senior Center, Carner Ave.
    • Continued working on redlines
    • Printed set for review
      • AXP Hours: 3 (Project Development & Documentation)
    • Charleston County Community Development & Housing Renovation
      • Began working on set of redlines to the reflected ceiling plan
        • AXP Hours: 1 (Project Planning & Design)

October 12, 2022 [4 Hours]

  • Colleton County Voter Registration Center
    • Began working on redlines as well as organizing sheets
      • AXP Hours: 4 (Project Planning & Design)

October 13, 2022 [4 Hours]

  • Colleton County Voter Registration Center
    • Began working on redlines as well as organizing sheets
      • AXP Hours: 2 (Project Planning & Design)
    • Cane Bay Catholic Church
      • Began scaling existing site images in preparation for a preliminary design phase
        • AXP Hours: 2 (Programming & Analysis)

 

Reflection

  • This week I worked mostly in production helping team members to meet deadlines as well as get drawing sets ready for submittals. Throughout this period, I learned a lot about time management and how to prioritize projects based on the scope of work and how much can be accomplished within a certain amount of time.