11/02
Hours worked: 4
Continued work on the Gifford Rosenwald School Revit model and renderings. Exterior modeling and site layout (parking, foliage, outdoor deck).
11/03
Hours worked: 0
11/04
Hours worked: 4
Continued work on the Gifford Rosenwald School Revit model and renderings. Exterior modeling and site layout (parking, foliage, outdoor deck).
11/05
Hours worked: 4
Continued work on the Gifford Rosenwald School Revit model and renderings. Exterior modeling and site layout (parking, foliage, outdoor deck).
Total AXP Weekly Hours: 12
Total AXP Hours: 144
Reflection: I’m nearing completion on the Gifford Rosenwald School renderings. Ben wanted the exterior shots as well, so I began modeling that portion of the project. The parking and car transportation is something I normally haven’t accounted for so it’s beneficial to get that experience.