George Sorbara + Cummings & McCrady, Inc. Architects 9/21/20 – 9/24/20

Daily Logs:

9/21

Hours worked: 4

Continued work on the CofC 107 Wentworth Fraternity House Revit model. Modeled a spiral exterior staircase, which is probably the most difficult feat I’ve accomplished in the program.

9/22

Hours worked: 0

9/23

Hours worked: 4

Continued work on the CofC 107 Wentworth Fraternity House Revit model. Began setting the exploded axonometric view up, as the model is near an adequate level of completion.

9/24

Hours worked: 4

Continued work on the CofC 107 Wentworth Fraternity House Revit model. Continued setting the exploded axonometric drawing up, as the model is near an adequate level of completion. Assisted in choosing the material palette for the Folly Beach City Hall Renovations project.

 

Total Hours Worked: 12

Total Overall Hours Worked: 64

Total AXP Hours: 64

 

Weekly Reflection: I’m getting pretty in tune with Revit, as I’ve been working with it for about three weeks now. The detailing of the ornamentation has been interesting and allowed me to see the importance in tending to details. The material palette selection gave me insight on reacting to client desires while still navigating them with your own expertise.

 