02/11/2019
Time worked: 4 hours
Tasks performed: Prepare documents to be sent to a sign manufacturer for a sign at 2453 King St.
Work accomplished: Project development and documentation (AXP hours)
02/12/2019
Time worked: 4 hours
Tasks performed: Prepare a collection of precedent office building with certain characteristics, typical materials used in the state of Georgia and site images for a schematic design session in the Savannah offices.
Work accomplished: Project development and documentation (AXP hours)
02/13/2019
Time worked: 4 hours
Tasks performed: Input property lines from a survey into a Revit file for a project in Charleston historic district. Later a visit to the Charleston Historic Foundation to ask of possible objections that we might encounter on that same project.
Work accomplished: Project development and documentation (AXP hours)
02/14/2019
Time worked: 4 hours
Tasks performed: A construction manager took me on a site visited to a 7-story student housing project at 595 king street. There he inspected the quality of the tile and brick finishes.
Work accomplished: Construction and evaluation (AXP hours)