1/30/20 –
Lucy Beckham H.S. Construction Administration.
Completed RFI’s by adding detail to sheets for Sound Absorbing Panels.
2/3/20 –
Lucy Beckham H.S. Construction Administration.
Completed RFI’s by adding Detail to sheets for sound absorbing panels.
2/4/20 –
Dorchester County School District Project Planning and Design.
Documentation of existing conditions in the schools within the county.
2/5/20 –
Dorchester County School District Project Planning and Design.
Documentation of existing conditions in the schools within the county.
2/6/20
Dorchester County School District Project Management.
Organized 360 photographs of existing conditions in the schools.
2/10/20
Dorchester County School District Project Management.
Organized 360 photographs of existing conditions in the schools.
2/11/20
Dorchester County School District Project Management.
Organized 360 photographs of existing conditions in the schools.
2/12/20
Punchlist at MUSC – Construction Evaluation
2/13/20
Dorchester Construction Evaluation
Lucy Beckham Construction Administration
Worked on ASI’s.
Total AXP Hours
Construction Administration – 16
Project Planning and Design – 4
Project Management – 16