DAILY LOGS
Monday, January 27
Hours Worked: 8:00 – 12:00 Total: 4 hours
- Revision – Carnes
AXP Category: Project Development & Documentation
Tuesday, January 28
Hours Worked: 8:00 – 2:00 Total: 6 hours
- River Avenue – as-built
- Office meeting
AXP Category: Project Development & Documentation and Practice Management
Wednesday, January 29
Hours Worked: 8:00 – 12:00 Total: 4 hours
- Revision – Carnes
- Update current insulation to spray insulation
AXP Category: Project Development & Documentation
Thursday, January 30
Hours Worked: 8:00 – 1:30 Total: 5.5 hours
- 3D Scanner – King Street Building
- Wendy’s – as-built
AXP Category: Project Development & Documentation and Construction & Evaluation
WEEKLY REFLECTION
For the past two weeks, I’ve been working on and updating construction documentation for four different gas stations within the area. While working on these projects, I’m starting to understand the relationship between working drawings and the built environment. I understand that cost plays a huge role in the construction phase, and updating the plans to reduce the cost is essential while reviewing a project. I also was able to use a 3D scanner, which is a laser projection system that creates a 3D world while walking around an existing structure.