Monday 4/11/22 Today I focused on wrapping up the site dimensions and provided where discrepancies I found in the field dimensions for the team to go and check AXP: Project Planning & Design Tuesday 4/12/22 Today I worked on design Schemes AXP: Project Planning & Design Wednesday 4/13/22 Today I worked on design Schemes AXP: […]
Author: nicolecoker
Week 9 – Coker, Nicole – Daily and Weekly Reflection
Monday 4/4/22 Today I focused on wrapping up the site dimensions and provided where discrepancies I found in the field dimensions for the team to go and check AXP: Project Development & Documentation Tuesday 4/5/22 Today I finished up the model edits. AXP: Project Development & Documentation Wednesday 4/6/22 Today I received the original drawings […]
Week 8 – Coker, Nicole – Daily & Weekly Reflection
Monday 3/28/22 Today I created a massing model to lower the height of an apartment building by two stories and extended the footprint. Community members in this area were concerned with the height and we are providing renderings to show what the building would look like minus two stories and extended over the car entrance. […]
Week 7 – Coker, Nicole – Daily & Weekly Blog
Monday 3/14/22 Today I created a bulkhead detail for the Russell House Project and continued cleaning up RCP’s and other items the model for our CD’s. AXP: Project Development & Documentation Tuesday 3/15/22 Today was a continuation of model and drawing updates. AXP: Project Development & Documentation Wednesday 3/16/22 Today I worked on fixing window […]
Week 6 – Coker, Nicole – Daily and Weekly Reflection
Monday 3/07/21 – Thursday 3/10/22 This week I am working on USC Russell House Dining to prep elevations, keynotes, Reflected Ceiling Plans & bathroom enlarged plans. Our CD deadline is approaching and we are getting everything detailed out for the set. AXP: Project Development and Documentation Week Reflection: This week I was able to capitalize […]
Week 1 – Coker, Nicole – Daily & Weekly Reflection
Monday 1/31/22 Today I continued pushing on elevations and setting them up on sheets for the 1801 Assembly Project. Our Design Development set is due on the 4th of February and will be used for initial pricing – so all casework and accessories need to be updated in order to be included. AXP: Project Development […]
Week 2 – Coker, Nicole – Daily & Weekly Reflection
Monday 2/7/22 After the big push for the Design Development set last week, there were a few things that needed edits with elevations and casework in the model. I spent my time working through those list of edits. AXP: Project Development & Documentation Tuesday 2/8/22 I finished up editing the elevations and other notes and […]
Week 3 – Coker, Nicole – Daily & Weekly Reflection
Monday 2/14/22 Today I worked on applying finishes to furniture, walls, and editing our screen wall for the booth seating to prep for the renderings that will be shown at the next client meeting for the Russell House AXP: Project Development & Documentation Tuesday 2/15/22 Today I worked on renderings for the Russell House Project […]
Week 4 – Coker, Nicole – Daily and Weekly Reflection
Monday 2/21/22 This week I continued working on layouts for the apartment building in Connecticut, but this time rearranging unit layouts to accommodate for the new elevator and stair locations. AXP: Programming and Analysis Tuesday 2/22/22 Today I jumped in on our Winston Salem Project to take a look at turning a once lobby into […]
Week 5 – Coker, Nicole – Daily & Weekly Reflection
Monday 2/28/22 This week I am working on USC Russell House Dining. We are looking at location options to accommodate the Dish Drop off carousel and reworking of bathroom locations because of these moves. AXP: Project Development and Documentation Tuesday 3/01/22 Today was all about Dish Drop off location and bathroom layouts. I also wrapped […]