Monday October 4th – Thursday October 7th

Weekly Entry: Log Summary – Delaney Skelly

Monday October 4th – Thursday October 7th

Time Worked:

  • Monday: 9-12 
  • Tuesday: 9 – 5
  • Wednesday: 9 – 12:30 
  • Thursday: 9 – 1

 

Tasks Performed

  • Monday I worked from home and completed the master bedroom renderings and design boards. 
  • Tuesday I organized fabrics in the office and cleaned up. I then picked out more furniture and edited and added design boards. I completed the updated master bedroom design board, kitchen design board, and started the bunk room design board. I am in charge of the bunk room bedroom completely on my own which is very exciting. 
  • Wednesday I edited and added our new furniture selections to the Furniture Plans for size and showed all of the dimensions. I did that for the entire house and prepared those for my boss to go to market next week 
  • Thursday I had my school midterm meeting with my boss in the morning. After that I organized all of our folders for my boss to go to the market next week. I organized all of our selections that the client needed to make at the market and gave them visuals, plans, and drawings for them to select.  

 

Work Accomplished (AXP HOURS EARNED) 

16 hours

Lessons Learned 

Learned about all the preparation that goes into the market and the responsibilities of bringing a client with the designer. 

 

Records of Work 

Project Title: Cumbaa Residence

Project Location: Johns Island

Project Scope: Large

Project Manager: Beverly Bohan

Role of the Student: Assist in design and technical needs. 

 