This week I worked on Signage for one of our school projects as a close out procedure and came up with a banner to hang over the walls in each stairwell. One issue is that there was wall equipment in different locations on each stairwell that couldn’t be covered. So for this task, I had to find the right sign height and width as not to cover up the wall equipment. After that, I found imagery to be printed on the banner. Based on photographs, I used blocks to located the wall equipment and created elevations to send to the client. I also worked on some general marketing for the firm and created project pages to be used in submittals. PD&D: 11hrs