Monday 9.14.2020

4 Hours Worked | CD Phase Redlines + Weekly Meeting | 2.5 AXP Hours

 

Tuesday 9.15.2020

4 Hours Worked | CD Phase Redlines | 4 AXP Hours

 

Wednesday 9.16.2020

4 Hours Worked | CD Phase Redlines | 4 AXP Hours

 

Thursday 9.17.2020

4 Hours Worked | CD Phase Redlines | 4 AXP Hours

 

 

Weekly Reflection:

This week while working at Rosenblum Coe Architects, we had a big push to complete 95% construction documents for one of our larger projects. While the drawing set was in solid condition already, it needed lots of updates with keynotes, specs and detailing. The first part of the week was spent working on interior and exterior elevations. I then moved to working on sections and details. While I had to ask a lot of questions to get started, I soon was able to learn about the project itself in great depth by working on the documents for it. Looking forward to what the next week will bring.