Week 9: 3/9/20 – 3/12/20

DAILY LOGS

Monday, March 9

Hours Worked: 8:00 – 12:00 Total: 4 hours

  • Update Canopy Design and renderings
  • Design Concept for Co-working space

AXP Category: Project Development & Documentation and Project Planning & Design

Tuesday, March 10

Hours Worked: 8:00 – 2:00 Total: 6 hours

  • Office Meeting
  • Update Renderings
  • Interior kickoff – lighting fixture meeting
  • Firm’s Charrette – Concept for coworking space

AXP Category: Project Development & Documentation, Project Planning & Design, and Project Management

Wednesday, March 11

Hours Worked: 8:00 – 12:00 and 4 – 5:30 Total: 5.5 hours

  • Client Meeting – Interior Design
  • Construction Documentation – ceiling plan

AXP Category: Project Development & Documentation and Project Management

Thursday, March 12

Hours Worked: 8:00 – 1:00  Total: 5 hours

  • Construction Documentation – ceiling plan
  • Office Room Layout – Option 1

AXP Category: Project Development & Documentation

WEEKLY REFLECTION

This week was a busy week at the office, but also an exciting experience. I not only worked on multiple projects, but I was able to focus on one project. I’ve learned how to correctly put together a ceiling plan and learned how the built environment could influence much of the design decisions. During the Site visit, I was able to see how the HVAC systems can change the way the interior design will look base on its placement. After meeting with the client and discussing different design options, we can now figure out a layout that will work base on its current condition.

 

 

 

Leave a Reply