Sept 24 – Sept 27 at SMHa Monday, Sept 26: Today, I went into Sketchup to create a large site model of the future “Point Hope Amenities” complex being built in Cainhoy. This is supposed to serve as an entrance to this community in Daniel Island. Jeff Johnston is creating and in construction of many […]
Month: October 2019
Sept. 16-19 @ SMHa
Sept 16 – Sept 19 at SMHa Monday, Sept 16: Today I continued the revisions and the addenda for the Hand Institute project and had Corrine Corte review them. She has worked closely to teach me how to better my skills in Revit specifically with interiors and she’s a wonderful mentor. AXP Hours: 4 PDD […]
Sept. 9-13 @ SMHa
Sept 9 – Sept 13 at SMHa Monday, Sept 9: Today, I worked on making an addendum for the project I have been working on throughout the summer, Hand Institute of Charleston. This project involves two doctors who are hand surgeons buying an empty shell of a building and designing their own office space to […]
TC Blog Post 10/7-10/10
Savannah Commons – 30×42 Sheets Mike Nixon – Project Lead Much easier to work with bigger sheets like this, especially when you’re getting into the minutia of the project. Like line weights and dashed lines. Savannah Commons Lobby Mike Nixon – Project Lead An example of plan sketches that I turn into actually digital […]
An odd little structure
Monday 7th 19 Logan (1h30 – Project Planning and Design) Point of Pines (1h30 – Project Planning and Design) Today for 19 Logan, I continued working on the plan of the house and exploring different layouts to enlarge certain rooms in the house and reduce others. I started up on a new project in point […]
Kelly Umutoni Weekly Entries – Lessons Learned : 10.07.2019 – 10.10.2019
Project title: Lennar Midtown Project Location: Charleston, SC Project manager: Luke Jarrett Role of the student: Help re-dimension sheet set per design changes. Lessons Learned In general, when drawing staircases leave enough room for the handrails. ( a minor detail that sometimes ruins hallways when overlooked)
Kelly Umutoni Daily logs : 10.07.2019 – 10.10.2019
Monday 10/07 Hours Worked: 4 hours Worked on fascia manufacturer research for a project AXP Hours: 4 hours: Project Development & Documentation Tuesday 10/08 Hours Worked: 6 hours Worked on setting up elevation sheet set AXP Hours: 6 hours: Project Development & Documentation Wednesday 10/09 Hours Worked: 4 hours Worked on re-dimensioning and cleaning up […]
Kelly Umutoni Weekly Entries – Lessons Learned : 09.30.2019 – 10.02.2019
Project title: Spectrum Sourcing Project Location: Raleigh, NC Project manager: Luke Jarrett Role of the student: Help research permit procedures in the city of Raleigh Lessons Learned This is more under ‘General Practice’: ope lessons that I got out of this week is that no one knows everything, even firms need clarification regarding building permit procedures.
Kelly Umutoni Daily logs : 09.30.2019 – 10.02.2019
Monday 09/30 Hours Worked: 4 hours Worked on relines for a sheet set. Worked on spec sheets redlines as well as schedules. AXP Hours: 4 hours: Project Development & Documentation Tuesday 10/01 Hours Worked: 6 hours Research permit research procedures for a new project in Raleigh as well as the architectural review process AXP Hours: […]
Week 7 – Cameron Foster
Overview: This week I have continued working on EP Lab red lines and adjustments of equipment within the labs to match vendor drawings as well as engineer drawings. This project has been a long process for me as I am the only person who is working on it with the guidance of our Project Manager, […]