This week I was able to go on a site visit of one of MPS’s new projects, Lucy Beckham High School. The construction was being done in several phases, so I was able to see where concrete was being poured, where the cmu was being placed and then to where electrical and drywall was being installed. My coworker Michelle was one of the lead architects on the project and was incredibly knowledgeable about the construction and site. She made a big point to look at the transitions as they are usually a big point with inspectors.

Weekly Log:

Monday

  • 1 Hour, Office wide meeting and K-12 Meeting
  • 2 Hours, Aloft, Setting up the Revit Model
  • 1 Hour, Programming for White Knoll High School

Tuesday

  • 2 Hour, Programming for White Knoll High School
  • 2.5 Hours, Lucy Beckham High School Site Visit

Wednesday

  • 1 Hour, Programming for White Knoll High School
  • 3 Hours, Charleston County Blake Tenement Building, Worked on re-organizing rooms

Thursday

  • 3.5 Hours, Started setting up model of city of Charleston for office-wide use
  • 0.5 Hours, Charleston County Blake Tenement Building, Worked on re-organizing rooms