Week 5 (Mar. 12 – Mar. 14)
After last week’s BAR Meeting, a few of the drawing sets were returned for revisions, and my task for the next week or so will be making those revisions with my advisor and mentor.
Time worked: 17.25 hrs
AXP category: Project Development & Documentation
Week 6 (Spring Break: Mar. 19 – Mar. 22)
This week I worked on reorganizing the layout of construction document sets for the next BAR approval. For three separate houses, I corrected existing and proposed conditions, incorporated photo documentation, and relabeled all the title blocks.
Time worked: 28.5 hrs
AXP category: Project Management, and Project Development & Documentation